Project: Lowestoft Gull Wing Bridge

Contractor: Farrans A CRH Company

Client: Suffolk County Council

Commencement: 2022

Completion: 2024

Value: £3,600,000

Project description:

Works include construction of main control tower building, works to install Sprinkler Tank, Works to install Plant room. This includes all RC work, such as installing formwork, reinforcement, and concrete.

Works to install decks to approaching carriageway including 3500 nr Concrete planks on pre-installed steel deck, Installing rebar and rebar mesh on top of planks, installing concrete to decks. Also installing precast edge parapets to decks. Works also to install drainage kerbs to decks and install concrete footpaths.

Lowestoft Gull Wing Bridge - image 1 Lowestoft Gull Wing Bridge - image 2 Lowestoft Gull Wing Bridge - image 3 Lowestoft Gull Wing Bridge - image 4 Lowestoft Gull Wing Bridge - image 5 Lowestoft Gull Wing Bridge - image 6 Lowestoft Gull Wing Bridge - image 7 Lowestoft Gull Wing Bridge - image 8 Lowestoft Gull Wing Bridge - image 9 Lowestoft Gull Wing Bridge - image 10 Lowestoft Gull Wing Bridge - image 11 Lowestoft Gull Wing Bridge - image 12